rehabilitation of 33/11KV Ubungo substation – Tanzania

client name

Tanzania Electric Supply Company

industry

Power

location

Tanzania

Ubungo Substation Rehabilitation

Award of the rehabilitation of 33/11 KV Ubungo substation.

Project scope

Solutions

Supply, installation, testing & commissioning of 33/11 KV GIS, 15 MVA 33/11 power transformer, SAS & protection, AC/DC and communication. 

Solutions

Flood warning

Environmental warning

Traffic monitoring

Smart waste

Smart water

Smart lighting

Smart energy

Smart irrigation

Crowd monitoring

Smart parking

Digital experience

Digital wayfinding

Showcasing heritage assets

Pedestrian access control & intrusion detection

Vehicular access control & intrusion protection

Solutions

15/20MVA 33/11KV Transformer

3x33KV GIS Panels

3x11KV GIS Panels with Bus Section

New building to accommodate 11KV and 33KV switchgears

AC/DC Rooms

Guard house according to approved design

Impact & results

The project upgrades the Ubungo substation capacity to ensure reliable power supply at a higher capacity.

Impact & results

  • Optimized infrastructure & operational efficiency
  • Optimized resource management
  • Seamless user experience for Diriyah’s residents and visitors
  • Contributing towards achieving the Kingdom’s Vision 2030
  • Optimized infrastructure & operational efficiency
  • Optimized resource management
  • Seamless user experience for Diriyah’s residents and visitors
  • Contributing towards achieving the Kingdom’s Vision 2030